Regulation 21 Closed periods – quantitative restrictions

(1)

Organic manure with high available nitrogen content must not be applied to land in excess of the maximum quantities set out in column 2 of the table in Schedule 4 in relation to the relevant manure during the following periods–

(a)

4 weeks prior to the first day on which regulation 20 prohibits the application of such manure; and

(b)

from the day following the last day of that prohibition until 14th February, both dates inclusive.

(2)

In any period during which a prohibition imposed by paragraph (1) applies in respect of land, there may be applied to that land only one of the types of organic manure specified in column 1 of that table.