In the local government area of North Lanarkshire—

  • Work No. 4—A road, being a raising of Carlisle Road (A 73), Airdrie, over the Drumgelloch-Helensburgh via Queen Street Low Level and Singer Railway commencing in that road at a point 53 metres south of the centre of the roundabout at the junction of that road with Clark Street, Motherwell Street and Forrest Street, and terminating in Carlisle Road at a point 150 metres south of the centre of that roundabout.

  • Work No. 5—A road forming a means of access from Calderrigg Road to the relocated Drumgelloch station.

  • Work No. 6—A road forming a means of access from Forrest Street to the new station car park at Drumgelloch.

  • Work No. 7—A road, being a raising of Towers Road, Clarkston, over the railway (Work No. 1) commencing in that road at a point 53 metres north-west of the junction of Dunrobin Road with Towers Road and terminating in Towers Road at a point 10 metres north of the junction of Katherine Street with Towers Road.

  • Work No. 8A—A temporary road at Clarkston, for the duration of the construction of Work No. 8B, commencing at a point in Katherine Park Lane 30 metres south of the south-eastern corner of Wester Moffat farm house, passing northwards and terminating in Katherine Park Lane at a point 137 metres south-east of the junction of that road with Forrest Street.

  • Work No. 8B—A road, being a raising of Katherine Park Lane, Clarkston, over the railway (Work No. 1), commencing in that road at a point 29 metres south of the south-eastern corner of Wester Moffat farm house, passing northwards over the railway (Work No. 1) and terminating in that road at a point 142 metres south-east of the junction of that road with Forrest Street. Work No. 8B includes a bridge over the railway (Work No. 1).

  • Work No. 9—A road at Plains commencing by a junction with Main Street (A 89) at a point 35 metres east of the junction of Meadowhead Road with Main Street (A 89) passing south-eastwards over the railway (Work No.1) then eastwards and terminating by a junction with Brownieside Road in that road at a point 47 metres south-east of the south-eastern corner of Brownieside Mill House. Work No. 9 includes a bridge over the railway (Work No.1).

  • Work No. 9A—A road at Plains commencing by a junction with the road (Work No. 9) passing eastwards and terminating at the entrance to the existing Express Dairies depot.

  • Work No. 10—A road at Plains commencing by a junction with Brownieside Road at a point in that road 21 metres south-east of the south-eastern corner of Brownieside Cottage, passing north-eastwards and terminating at the entrance to Ford Farm, Loadmanford.

  • Work No. 11—A road at Plains commencing by a junction with the road (Work No.12) at a point in Station Road 69 metres south-east of the junction of that road with Main Street (A89), passing north-eastwards and terminating at a point 65 metres north-east of the junction of Station Road with Main Street (A89).

  • Work No. 12—A realignment of Station Road, Plains, commencing in that road at a point 65 metres south-east of its junction with Main Street (A89), passing north-westwards and terminating in Station Road at a point 41 metres south-east of its junction with Main Street.

  • Work No. 13—A footbridge over the railway (Work No. 1) at Plains to provide a link between Main Street (A89), Brownieside Road and Plains Country Park commencing by a junction with Main Street (A89), passing south-eastwards then south-westwards and terminating by a junction with Station Road.

  • Work No. 14—A temporary realignment of Main Street (A 89)/Airdrie Road (A 89) east of Plains, commencing in Main Street at a point 315 metres north-east of Ford Bridge, passing westwards, then south-westwards and terminating in Airdrie Road (A89) at a point 94 metres north-east of Ford Bridge. Work No. 14 includes a bridge over the railway (Work No. 1).

  • Work No. 15—A temporary realignment of the Caldercruix Sewage Works and Easterton Farm access road commencing in that access road at a point 98 metres north of its junction with Airdrie Road (A89), passing generally northwards and terminating in that access road at a point 172 metres north of that road junction.

  • Work No. 16—A realignment of Airdrie Road (A 89), Caldercruix commencing in that road at a point 198 metres east of the entrance to Clints Farm, passing westwards and terminating in that road at a point 19 metres east of that farm entrance.

  • Work No. 16A—An access road at Caldercruix commencing by a junction with the realigned Airdrie Road (Work No. 16) at a point 119 metres east of the entrance to Clints Farm, passing northwards over North Calder Water, and terminating at Caldercruix at a point 192 metres north-east of that farm entrance. Work No. 16A includes a bridge over North Calder Water.

  • Work No. 18—An improvement of Main Street, Caldercruix, commencing at a point in that road at its junction with Airdrie Road (A 89), passing northwards over North Calder Water and terminating in Main Street at a point 30 metres west of the junction of Church Place with Main Street. Work No. 18 includes a bridge over North Calder Water.

  • Work No. 19—A road, being a raising of Main Street, Caldercruix, over the railway (Work No. 1), commencing in Main Street at a point 38 metres north-east of the junction of Millstream Crescent with Main Street, passing in a north-easterly direction over the railway (Work No. 1) and terminating in Main Street at a point 10 metres north-east of the junction of Station Road with Main Street. Work No. 19 includes a bridge over the railway (Work No. 1).

  • Work No. 20A—A temporary road at Hillend, for the duration of the construction of Work No. 20B, commencing in the unnamed road between Airdrie Road (A 89) and Hillend Reservoir Car Park at a point 122 metres north of the junction of that road with Airdrie Road, passing northwards and terminating in that unnamed road at a point 269 metres north of that road junction.

  • Work No. 20B—A road, being a raising of the unnamed road between Airdrie Road (A 89) and Hillend Reservoir Car Park, over the railway (Work No. 1), commencing in that unnamed road at a point 122 metres north of its junction with Airdrie Road, passing northwards over the railway (Work No. 1), and terminating in that unnamed road at a point 269 metres north of that road junction. Work No. 20B includes a bridge over the railway (Work No. 1).

  • Work No. 21—A footbridge over the railway (Work No. 1) at Hillend Fishing Lodge between Airdrie Road (A89) and Hillend Angling Club.

  • Work No. 22A—A temporary road at Forrestfield, for the duration of the construction of Work No. 22B, commencing by a junction with Airdrie Road at a point 25 metres west of the existing junction of Woodside Road with Airdrie Road (A 89), passing northwards and terminating by a junction with Work No. 23.

  • Work No. 22B—A road, being a raising of Woodside Road, Forrestfield, over the cyclepath (Work No. 2F) and the railway (Work No. 1), commencing at the junction of Airdrie Road (A 89) with Woodside Road, passing northwards over the cyclepath (Work No. 2F) and the railway (Work No. 1), and terminating by a point in Woodside Road 165 metres north of that junction. Work No. 22B includes a bridge over the cyclepath (Work No. 2F) and the railway (Work No. 1).

  • Work No. 23—An access road at Forrestfield, commencing by a junction with Woodside Road at a point 165 metres north of the junction of that road with Airdrie Road (A89), passing southwards then westwards and terminating at a point 140 metres south-west of its commencement.

  • Work No. 24—A road at Raiziehill, commencing at a point adjacent to the property known as Raiziehill, passing northwards, then eastwards and terminating by a junction with the track between the unnamed road and the property known as Raiziehill at a point 82 metres north of that property.