OpenLegislation

Paragraph 25 I1

England, Wales and Scotland

A specified work is to be constructed (and in the case of any temporary work removed) only in accordance with—

(a)

the approved plans (and, in the case of plans relating to sewers approved, deemed to have been approved or settled by arbitration, as amended from time to time by agreement between the promoter and the specified undertaker); and

(b)

all reasonable requirements made by the specified undertaker for the alteration, or otherwise for the protection, of the apparatus, or for securing access to it.

and an officer of the specified undertaker is entitled to watch and inspect the carrying out of the work.

Annotations

Commencement

I1

Sch. 10 para. 25 in force at 9.1.2014, see art. 1