Paragraph 3 I1

England and Wales

(1)

No works shall commence until a written scheme of investigation for areas of archaeological interest has been submitted to and approved by the local planning authority in consultation with English Heritage.

(2)

The scheme must include:

(a)

the scope and methodology for the carrying out of any measures identified under paragraph 2(2)(c);

(b)

details of the measures required to be taken to protect, record or preserve any significant archaeological remains that may be found.

(3)

Any archaeological field work or watching brief identified under the scheme must be carried out—

(a)

by a suitably qualified person or body approved by the local planning authority, and

(b)

in accordance with the approved scheme.

Annotations

Commencement

I1

Sch. para. 3 in force at 3.12.2014, see art. 1