Paragraph 9 Surface water drainageI1
England and Wales
The authorised development, save for the permitted preliminary works, must not be commenced until a final version of the drainage strategy has been submitted to and approved in writing by the Board. The onshore parts of the authorised development shall be implemented in accordance with the approved drainage strategy.
The final version of the drainage strategy submitted and approved under sub-paragraph (1) must be in accordance with the drainage strategy.
In this requirement, “the permitted preliminary works” means—
works consisting of the removal of existing structures and site clearance works; and
works consisting of any part of the off-site mitigation works, the installation of wheel cleaning facilities, the installation and diversion of utility services, surveys and the provision of temporary contractors’ facilities.