Paragraph 13 Percussive piling reporting protocolI1

England and Wales

(1)

The undertaker must submit weekly reports to the MMO of the duration of percussive piling that is undertaken on any given day on which piling takes place during the construction of the authorised development, unless otherwise agreed in writing with the MMO.

(2)

The reports submitted to the MMO pursuant to sub–paragraph (1) must include a log of the number and approximate location of piling rigs which are in operation on any given day, along with the number of piles driven.

(3)

The undertaker will hold fortnightly meetings with the MMO to discuss the weekly reports submitted under sub-paragraph (1) and agree any corrective action if required, unless otherwise agreed in writing with the MMO.

(4)

Subject to sub–paragraph (5), where percussive piling is paused, the recommencement of the percussive piling shall be subject to the provisions of sub–paragraph (1)(a) of paragraph 12 (“the contingency period”).

(5)

The contingency period must not exceed a total of 80 minutes in any given day on which percussive piling takes place.