Paragraph 122 Consultation and notificationI1

England and Wales

The undertaker must, at least 28 days before the undertaker commences the construction of any authorised work, or any phase of any authorised work, that has been assessed in any environmental document as being likely to interfere with DFDS’ use of the Port of Immingham or the surrounding road network, inform DFDS in writing stating what is proposed and have regard to any response received from DFDS.