OpenLegislation

Paragraph 140 InterpretationI1

England and Wales

The undertaker must compensate the Board in respect of all costs, charges and expenses that the Board may reasonably incur, have to pay or may sustain—

(a)

in the examination or approval of plans and evidence under this Part of this Schedule;

(b)

in inspecting the proposed site for and construction of any specified work or any protective works required by the Board under this Part of this Schedule; and

(c)

in carrying out of any surveys or tests by the Board that are reasonably required in connection with the authorised development and/or construction of the specified work.

Annotations

Commencement

I1

Sch. 4 para. 140 in force at 25.10.2024, see art. 1