Paragraph 4 Commencement of Tidal WorksI1
England and Wales
Any operations for the construction of any tidal work approved in accordance with this Order, once commenced, must be carried out by the undertaker without unnecessary delay and to the reasonable satisfaction of the Statutory Conservancy and Navigation Authority so that river traffic, the flow or regime of the river and the exercise of the Statutory Conservancy and Navigation Authority’s functions do not suffer more interference than is reasonably practicable, and an authorised officer of the Statutory Conservancy and Navigation Authority is entitled at all reasonable times, on giving such notice as may be reasonable in the circumstances, to inspect and survey such operations.
Annotations
Commencement
- I1
Sch. 4 para. 4 in force at 25.10.2024, see art. 1