Paragraph 54 CooperationI1
England and Wales
Where practicable, the undertaker and Northern Powergrid will make reasonable efforts to liaise and co-operate in respect of information that is relevant to the safe and efficient construction of the authorised development. Such liaison shall be carried out where any works are:
(a)
within 15m of any above ground apparatus; and/or
(b)
are to a depth of between 0–4m below ground level.
Annotations
Commencement
- I1
Sch. 4 para. 54 in force at 25.10.2024, see art. 1