Paragraph 7 Removal etc. of the Statutory Conservancy and Navigation Authority ’s moorings and buoysI1
England and Wales
If—
by reason of the construction of any tidal work it is reasonably necessary for the Statutory Conservancy and Navigation Authority to incur reasonable costs in temporarily or permanently altering, removing, re-siting, repositioning or reinstating existing moorings or aids to navigation (including navigation marks or lights) owned by the Statutory Conservancy and Navigation Authority, or laying down and removing substituted moorings or buoys, or carrying out dredging operations for any such purpose, not being costs which it would have incurred for any other reason; and
the Statutory Conservancy and Navigation Authority gives to the undertaker not less than 28 days’ notice of its intention to incur such costs, and takes into account any representations which the undertaker may make in response to the notice within 14 days of the receipt of the notice,
the undertaker must pay the costs reasonably so incurred by the Statutory Conservancy and Navigation Authority.
Annotations
Commencement
- I1
Sch. 4 para. 7 in force at 25.10.2024, see art. 1