Paragraph 9 Removal of temporary worksI1
England and Wales
On completion of the construction of any part of a permanent authorised work, the undertaker must as soon as practicable remove—
(a)
any temporary tidal work carried out only for the purposes of that part of the permanent work; and
(b)
any materials, plant and equipment used for such construction,
and must make good the site to the reasonable satisfaction of the Statutory Conservancy and Navigation Authority.
Annotations
Commencement
- I1
Sch. 4 para. 9 in force at 25.10.2024, see art. 1