Article 15 Access to worksI1

England, Wales and Scotland

The undertaker may, for the purposes of the authorised project—

(a)

form and lay out the permanent means of access, or improve existing means of access, in the locations specified in Part 1 (permanent means of access to works) of Schedule 9 (access to works);

(b)

form and lay out the temporary means of access in the locations specified in Part 2 (temporary means of access to works) of Schedule 9; and

(c)

with the consent of the relevant planning authority (such consent not to be unreasonably withheld or delayed), after consultation with the relevant highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised project.

Annotations

Commencement

I1

Art. 15 in force at 27.2.2025, see art. 1