Paragraph 25 Works not in accordance with this Part of this ScheduleI1
England, Wales and Scotland
If there is any failure by the undertaker to obtain consent or comply with conditions imposed by the Agency in accordance with this Part of this Schedule and where the Agency acting reasonably considers it necessary to avoid any of the risks specified in sub-paragraph (2) arising from the absence of such consent or from such non-compliance, the Agency may serve written notice requiring the undertaker to immediately cease all or part of the specified works to which the consent or conditions relate, as the same may be specified within the notice served, and the undertaker must immediately cease constructing such specified works or part of them until such time as it has obtained the consent or complied with the condition specified within the notice served unless the undertaker concludes, acting reasonably, that immediate cessation of the specified works or part of them would cause greater environmental damage than proceeding with the work in question and in those circumstances the undertaker must immediately serve a counter-notice on the Agency specifying its reasoning for reaching that conclusion.
The risks specified in sub-paragraph (1) are—
risk of flooding;
risk of harm to the environment; and
risk of detrimental impact on drainage.
If any part of a specified work, or any protective work required by the Agency pursuant to this Part of this Schedule, is constructed otherwise than in accordance with the requirements of this Part of this Schedule, the Agency may by notice in writing require the undertaker, at the undertaker’s own expense, to comply with the requirements of this Part of this Schedule or (if the undertaker so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the Agency reasonably requires.
Subject to sub-paragraph (5) if, within a reasonable period, being not less than 28 days beginning with the date when a notice under sub-paragraph (3) is served upon the undertaker, the undertaker has failed to begin taking steps to comply with the requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the Agency may execute the works specified in the notice and any reasonable expenditure incurred by the Agency in so doing is recoverable from the undertaker.
In the event of any dispute as to whether sub-paragraph (4) is properly applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the Agency must not except in the case of an emergency exercise the powers conferred by sub-paragraph (4) until the dispute has been finally determined in accordance with paragraph 32 (disputes).