Paragraph 33 ApplicationI1
England, Wales and Scotland
For the protection of Northern Powergrid, unless otherwise agreed in writing between the undertaker and Northern Powergrid, the following provisions have effect for the duration of the construction of the authorised works, including—
where a diversion or replacement of Northern Powergrid’s apparatus directly related to the authorised project is required during the construction phase of this Order and is undertaken pursuant to this Order (or any related correction or non-material amendment order); and
where decommissioning works of Northern Powergrid’s apparatus directly related to the authorised project are required and are undertaken pursuant to this Order (or any related correction or non-material amendment order),
the following provisions have effect for as long as it takes for the diversion, replacement or decommissioning to be completed.
Annotations
Commencement
- I1
Sch. 14 para. 33 in force at 27.2.2025, see art. 1