Paragraph 44 MiscellaneousI1
England, Wales and Scotland
Where practicable, the undertaker and Northern Powergrid will make reasonable efforts to liaise and co-operate in respect of information that is relevant to the safe and efficient construction of the authorised development. Such liaison must be carried out where any works are—
(a)
within 15 m of any above ground apparatus; or
(b)
are to a depth of between 0-4 m below ground level.
Annotations
Commencement
- I1
Sch. 14 para. 44 in force at 27.2.2025, see art. 1