Paragraph 6 Construction environmental management planI1
England, Wales and Scotland
No works forming part of Work No. 1 outside of the UK marine area (except the clearance of trees or other vegetation from Long Strip) may be commenced until a construction environmental management plan for that part of the works has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency on matters related to its function; and any such construction environmental management plan and the construction environmental management plan submitted pursuant to paragraph 8 of Part 2 (conditions applying to all licensable activities) of Schedule 3 (deemed marine licence) may be comprised in the same document.
No works forming part of Work No. 2 (except the clearance of trees or other vegetation from Long Strip), Work No. 3, Work No. 4, Work No. 5, Work No. 6, Work No. 7, Work No. 8 or Work No. 9 may be commenced until a construction environmental management plan for those works has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency and Natural England on matters related to their functions.
Any construction environmental management plan submitted and approved under sub-paragraph (1) and (2) must be substantially in accordance with the outline construction environmental management plan.
Any works forming part of Work No. 1 outside of the UK marine area, Work No. 2, Work No. 3, Work No. 4, Work No. 5, Work No. 6, Work No. 7, Work No. 8 and Work No. 9 must be carried out in accordance with the approved construction environmental management plan for those works, unless otherwise approved by the relevant planning authority.
The clearance of trees or other vegetation from Long Strip must be carried out in accordance with the Long Strip construction environmental management plan, unless otherwise approved by the relevant planning authority.