OpenLegislation

Paragraph 8 Highway worksI1

England, Wales and Scotland

(1)

Before the construction of any works to a highway maintainable at the public expense begins, written details of those works, including a plan of any land which is not such highway but which it is proposed for the purposes of article 10 (construction and maintenance of new, altered or diverted streets) is to become such highway on completion of those works, must be submitted to and approved by the relevant planning authority following consultation with the highway authority on matters related to its functions.

(2)

Before the construction of the underground culvert forming part of Work No. 4 begins, written details of the design of such underground culvert, back-filling and making good to the highway and the construction methodology for its installation must be submitted to and approved by the relevant planning authority following consultation with the highway authority on matters related to its functions.

(3)

The works referred to in sub-paragraph (1) and the underground culvert, back-filling and making good referred to in sub-paragraph (2) must be constructed in accordance with the approved details, unless otherwise approved by the relevant planning authority following consultation with the highway authority on matters related to its function.

Annotations

Commencement

I1

Sch. 2 para. 8 in force at 27.2.2025, see art. 1