Paragraph 6 Substation worksI1

England and Wales

(1)

Construction of Work No. 31A must not commence until details of—

(a)

the layout;

(b)

scale;

(c)

proposed finished ground levels;

(d)

hard surfacing materials;

(e)

the dimensions, colour and materials used for the buildings;

(f)

security fencing;

(g)

vehicular and pedestrian access, parking and circulation areas; and

(h)

proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports;

have been submitted to and approved by the relevant planning authority following consultation with Natural Resources Wales as appropriate.

(2)

The details submitted under sub-paragraph (1) of this requirement must be in accordance with requirement 7 (detailed design parameters onshore) and substantially in accordance with the design principles document.

(3)

Work No. 31A must be carried out in accordance with the approved details.

Annotations

Commencement

I1

Sch. 2 para. 6 in force at 11.10.2023, see art. 1