Paragraph 6 Substation worksI1
England and Wales
Construction of Work No. 31A must not commence until details of—
the layout;
scale;
proposed finished ground levels;
hard surfacing materials;
the dimensions, colour and materials used for the buildings;
security fencing;
vehicular and pedestrian access, parking and circulation areas; and
proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports;
have been submitted to and approved by the relevant planning authority following consultation with Natural Resources Wales as appropriate.
The details submitted under sub-paragraph (1) of this requirement must be in accordance with requirement 7 (detailed design parameters onshore) and substantially in accordance with the design principles document.
Work No. 31A must be carried out in accordance with the approved details.
Annotations
Commencement
- I1
Sch. 2 para. 6 in force at 11.10.2023, see art. 1