Schedule 6 Land of which only temporary possession may be takenI1
England and Wales
In the County of Denbighshire:
| (1) Number of plot shown on land plans | (2) Purpose for which temporary possession may be taken | (3) Relevant part of authorised development |
|---|---|---|
| 2 | Temporary use as a construction working area, use for cable installation vessel anchoring and for access to facilitate construction of Work Nos. 2A, 3 and 4 | Work No. 3A |
| 3, 4, 5, 24, 27 | Temporary use as a construction working area, use for cable installation vessel anchoring and for access to facilitate construction of Work Nos. 2A, 3 and 4 | Work Nos. 3A and 6 |
| 37, 38, 39, 40, 43, 44, 45, 46 | Temporary use as a construction working area, use for cable installation vessel anchoring and for access to facilitate construction of Work Nos. 2A, 3, 4, 5 and 41 | Work Nos. 3A and 7 |
| 7, 9, 10, 13, 15, 16, 17, 18, 19, 20, 21, 22, 23, 25, 88 | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 2A, 3, 4, 5, 7 and 41 | Work No. 6 |
| 92, 93, 94, 95, 96, 98 | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 5 and 7 | Work No. 6 |
| 15 | Temporary use as a construction working area, use as a temporary construction compound and for access to facilitate construction of Work Nos. 2A, 3, 4, 5, 7 and 41 | Work Nos. 6 and 6A |
| 47, 49, 50, 52, 54, 57, 59, 60, 62, 64, 65, 67, 68, 69, 70, 71, 72, 73, 74 , 79, 80, 81, 84, 85, 86 | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 2A, 3, 4, 5, 7 and 41 | Work No. 7 and temporary mitigation area |
| 75 | Temporary use as a construction working area, use as a temporary construction compound and for access to facilitate construction of Work Nos. 2A, 3, 4, 5, 7 and 41 | Work Nos. 7 and 7A |
| 104, 107, 108, 109, 110, 111, 112, 113, 117, 121, 122, 123, 124, | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 5, 8, 8A, 9 and 41 | Work No. 8 |
| 119, 127, 130, 132, 133, 137, 138 | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 9, 11 and 41 | Work No. 10 |
| 120, 128 | Temporary use as a construction working area, use as a temporary construction compound and for access to facilitate construction of Work Nos. 9, 11 and 41 | Work No. 10A |
| 159, 161 | Temporary use as a construction working area and for access to facilitate construction of Work No. 11 | Work No. 12 |
| 170, 171, 172, 173, 176, 181, 182 | Temporary use as a construction working area and for access to facilitate construction of Work No. 11 and temporary mitigation area | Work No. 13 and temporary mitigation area |
| 195, 197, 205 | Temporary use as a construction working area, use as a temporary construction compound and for access to facilitate construction of Work Nos. 11, 15 and 41 and temporary mitigation area | Work Nos. 14, 14A and temporary mitigation area |
| 210, 211, 212, 215, 218, 219 | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 11, 15 and 41 and temporary mitigation area | Work No. 14 and temporary mitigation area |
| 221, 237 | Temporary use as a construction working area, use as a temporary construction compound and for access to facilitate construction of Work Nos. 11, 15 and 41 | Work Nos. 16 and 16A |
| 223, 224, 227, 228, 229, 230, 231, 232, 234 | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 11, 15 and 41 | Work No. 16 |
| 248, 249, 251, | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 15, 18 and 41 | Work No. 17 |
| 270, 271, 273, 274 | Temporary use as a construction working area for drainage during construction of Work No. 19 | Associated development (f) for Work No. 19 |
| 276, 277, 279, 282 | Temporary use as a construction working area, use as a temporary construction compound and for access to facilitate construction of Work Nos. 19, 21 and 41 | Work Nos. 20 and 20A |
| 283, 284, 289, 290 | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 19, 21 and 41 | Work No. 20 |
| 303 | Temporary use as a construction working area for drainage during construction of Work No. 21 | Associated development (f) for Work No. 21 |
| 307, 308, 313 | Temporary use as a construction working area, use as a temporary construction compound and for access to facilitate construction of Work Nos. 21, 23 and 41 | Work Nos. 22 and 22A |
| 310, 311, 312, 314, 315, 323, 324, 325, 326, 327, 328, 329 | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 21, 23 and 41 | Work No. 22 |
| 357 | Temporary use as a construction working area for drainage during construction of Work No. 23 | Associated development (f) for Work No. 23 |
| 330, 331, 332, 333, 334, 338, 339, 340, 341, 343, 345 | Temporary use to improve visibility splays and for access to facilitate construction of Work Nos. 23 and 41 | Work No. 24 |
| 348, 350, 351, 352 | Temporary use a construction working area and for access to facilitate construction of Work No. 23 | Work No. 25 |
| 369, 370, 375 | Temporary use as a construction working area, use as a temporary construction compound and for access to facilitate construction of Work Nos. 23 and 41, and temporary mitigation area | Work Nos. 26, 26A and temporary mitigation area |
| 404, 405, 406, 411, 414 | Temporary use as a construction working area and for access to facilitate construction of Work Nos. 23 and 41, and temporary mitigation area | Work No. 27 and temporary mitigation area |
| 424, 433, 434 | Temporary use as a construction working area, use as a temporary construction compound and for access to facilitate construction of Work Nos. 33, 34, 36 and 41, and temporary mitigation area | Work Nos. 37, 37A and temporary mitigation area |
| 441, 442, 443, 449, 450, 451, 452, 454, 455 | Temporary use to improve visibility splays and for access to facilitate construction of Work Nos. 36 and 41, and temporary mitigation area | Work No. 38 and temporary mitigation area |
| 463, 464 | Temporary use as a construction working area, use as a temporary construction compound, improvement of existing accesses and for access to facilitate construction of Work Nos. 36, 40 and 41, and temporary mitigation area | Work Nos. 39, 39A and temporary mitigation area |
| 474, 475. 476, 477, 493, 494, 495, 498, 499 | Temporary use as a construction working area, improvement of existing accesses and for access to facilitate construction of Work Nos. 36, 40 and 41, and temporary mitigation area | Work No. 39 and temporary mitigation area |
Annotations
Commencement
- I1
Sch. 6 in force at 11.10.2023, see art. 1