OpenLegislation

Paragraph 152 I1

The undertaker must provide the Company with the actual as-laid route of the undertaker cables in the vicinity of the Company cables by—

(a)

provision of co-ordinates of the crossing points within 48 hours after completion of installation of the undertaker cables within a 250 metre radius from the crossing points; and

(b)

provision of charted information of the crossing points as soon as practicable after the completion of the installation of the undertaker cables.

Annotations

Commencement

I1

Sch. 9 para. 152 in force at 11.10.2023, see art. 1