Paragraph 154 Future specified workI1

England and Wales

Following the installation of the undertaker cables, the undertaker must use all reasonable endeavours to consult the Company in good faith regarding any future specified work which may be required to the undertaker cables. The undertaker and Company must work together to accommodate any such future specified work if this is required and must use all reasonable endeavours to agree the timings and methods for any future specified work to be undertaken, such agreement not to be unreasonably withheld or delayed by the Company.

Annotations

Commencement

I1

Sch. 9 para. 154 in force at 11.10.2023, see art. 1