OpenLegislation

Paragraph 95 I1

England and Wales

The undertaker will give Conwy County Borough Council not less than 7 working days’ notice of the anticipated start date for offshore piling works forming part of the authorised development.

Annotations

Commencement

I1

Sch. 9 para. 95 in force at 11.10.2023, see art. 1