OpenLegislation

Paragraph 154 Retained apparatus: protection

Original text. Later amendments are not shown.

The undertaker must give to VDEC not less than 28 days’ written notice of its intention to commence the construction of any specified works and, not more than 14 days after completion of their construction, must give VDEC written notice of the completion.