Paragraph 10 Surface and foul water drainage
(1)
No part of the authorised development may commence until written details of the surface water drainage scheme and (if any) foul water drainage system (both of which must be in accordance with the principles in the outline drainage strategy) have been submitted to and approved by the relevant planning authority for that part, such approval to be in consultation with Anglian Water Services Limited and the Environment Agency.
(2)
Any approved scheme must be implemented as approved and maintained throughout the construction and operation of the authorised development.