Paragraph 9 Fencing and other means of enclosure

Original text. Later amendments are not shown.

(1)

No part of the authorised development may commence until written details of all proposed temporary fences, walls or other means of enclosure have been submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.

(2)

No part of the authorised development may commence until written details of all permanent fences, walls or other means of enclosure for that part (which must be in accordance with the relevant outline design principles) have been submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.

(3)

For the purposes of sub-paragraph (1), “commence” includes any permitted preliminary works.

(4)

Any construction site must remain securely fenced in accordance with the approved details under sub-paragraph (1) at all times during construction of the authorised development.

(5)

Any temporary fencing must be removed on completion of the part of construction of the authorised development for which it was used.

(6)

Any approved permanent fencing in a part must be completed before the date of completion in respect of such part.