Regulation 7 Requirements for new-build propertiesI1
England and Wales
A property meets the requirements in this regulation where the building—
was built principally with the use of the labour or resources of the first owner (including where the resource was a loan which the first owner was liable to repay), F2...
has not, while it was built or at any subsequent time been owned wholly or partly by a person who is not an individual F3, and
is not part of an excluded property development.
In this regulation—
“excluded property development” means a development of multiple buildings constructed on a plot acquired from a person who decided or offered the plans or specifications to which the buildings were wholly or mainly built.
Annotations
Textual amendments
- F1
Reg. 7 renumbered as reg. 7(1) (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 7(a) (with reg. 25)
- F2
Word in reg. 7(1)(a) omitted (8.5.2024) by virtue of The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 7(b) (with reg. 25)
- F3
Word in reg. 7(1)(b) inserted (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 7(c) (with reg. 25)
- F4
Reg. 7(1)(c) inserted (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 7(d) (with reg. 25)
- F5
Reg. 7(2) inserted (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 7(e) (with reg. 25)
Commencement
- I1
Reg. 7 in force at 23.5.2022, see reg. 1(1)