Paragraph 15 Phasing of construction and commissioning of Work Nos. 1 and 2

Original text. Later amendments are not shown.

(1)

Subject to sub–paragraph (2), no part of the authorised development may commence until a phasing programme setting out the commencement of construction and the anticipated start of commissioning and the anticipated date of final commissioning for each of Work Nos. 1 and 2 has been submitted to and approved by the relevant planning authority.

(2)

The phasing programme must provide for the anticipated date of final commissioning of Work Nos. 1 and 2 as soon as reasonably practicable. The phasing programme must be implemented as approved by the relevant planning authority.