Paragraph 21 Combined heat and power
On the date that is 12 months after the date of final commissioning for Work No. 1A, the undertaker must submit to the relevant planning authority for its approval, following consultation with Boston Borough Council, a report (“the CHP review”) updating the combined heat and power assessment.
The CHP review submitted and approved must—
consider whether opportunities reasonably exist for the export of heat from numbered Work 1A; and
include a list of actions (if any) that the undertaker is reasonably required to take (without material additional cost to the undertaker) to increase the potential for the export of heat from Work No. 1A.
The undertaker must take such actions as are included, within the timescales specified, in the approved CHP review.
On each date during the operation of Work No. 1A that is five years after the date on which it last submitted the CHP review or a revised CHP review to the relevant planning authority, a revised CHP review must be submitted to and approved by the relevant planning authority, following consultation with Boston Borough Council.
Sub-paragraphs (2) and (3) apply in relation to a revised CHP review submitted under sub-paragraph (4) in the same way as they apply in relation to the CHP review submitted under sub-paragraph (1).