Paragraph 5 Parameters of authorised development
The elements of the authorised development listed in column (1) of the table below (design parameters) must not exceed the maximum dimensions and levels and, where applicable, the minimum dimensions, set out in relation to that element in columns (3) to (6) of that table.
| (1) Element of authorised development | (2) Work No. | (3) Maximum length (metres) | (4) Maximum width (metres) | (5) Maximum height (metres) from ground level unless stated | (6) Minimum height (metres) from ground level unless stated |
|---|---|---|---|---|---|
| Main energy recovery facility buildings (3 No. units, dimensions per unit) | 1A | 105 | 35 | 44 | – |
| Energy recovery stacks (3 No.) | 1A(a)(iv) | – | – | 80 | 80 |
| Turbine building | 1A(a)(v) | 53 | 40 | 20 | – |
| Air cooled condenser array | 1A(a)(vii) | 65 | 45 | 30 | – |
| Ash processing building | 1B | 70 | 30 | 32 | – |
| Carbon dioxide recovery building | 1C | 30 | 20 | 12 | – |
| Lightweight aggregates main building | 2 | 75 | 40 | 44 | – |
| Lightweight aggregates storage silos | 2(a), 2(e) | 6 | 6 | 25 | – |
| Lightweight aggregates stacks (2 No.) | 2(d) | – | – | 80 | 80 |
| Electrical substation | 3 | 95 | 35 | – | – |
| Wharf structure | 4(a) | 400 | – | – | 7.2 (AOD) |
| Supporting buildings and facilities (control room, visitor centre, workshops) | 5 | 40 | 20 | 15 | – |