England, Wales and Scotland

(1)

No authorised development shall commence until a scheme of archaeological investigation has been submitted to and approved by the relevant planning authority.

(2)

The scheme of archaeological investigation shall incorporate—

(a)

a walkover survey before commencement of the authorised development;

(b)

trial trenches at the sites of wind turbines W13, W17, W18, W19 and W23; and

(c)

a watching brief during construction to record both established archaeological remains and any remains subsequently identified as present.

(3)

The scheme of archaeological investigation shall be implemented as approved.