Paragraph 7 IndemnityI1

England, Wales and Scotland

(1)

If by reason or in consequence of the construction of any such works authorised by this Order or in consequence of the construction, use, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Order or any subsidence resulting from any of these works), any damage is caused to any apparatus or property of the protected person, or there is any interruption in any service provided, or in the supply of any goods, by any protected person, or the protected person becomes liable to pay any amount to any third party, the undertaker shall—

(a)

bear and pay on demand the cost reasonably incurred by the protected person in making good such damage or restoring the supply; and

(b)

indemnify the protected person for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from the undertaker, by reason or in consequence of any such damage or interruption or the protected person becoming liable to any third party as aforesaid.

(2)

The fact that any act or thing may have been done by a protected person on behalf of the undertaker or in accordance with a plan approved by a protected person or in accordance with any Requirement of the protected person or under its supervision shall not, excuse the undertaker from liability under the provisions of sub-paragraph (1) except where such act or thing done has been done as a result of the negligence of the protected person.

(3)

The protected person shall give the undertaker reasonable notice of any such claim or demand and no settlement or compromise shall be made without first consulting the undertaker and taking into account its representations.

(4)

Not commence construction (and not to permit the commencement of such construction) of the authorised works on any land either owned by the protected person in respect of which the protected person has an easement or wayleave for their Apparatus or any other interest or to carry out any works within 15 metres of the protected person’s Apparatus unless and until the protected person is satisfied acting reasonably (but subject to all necessary regulatory constraints) that the undertaker has procured acceptable insurance (and provided evidence to the protected person that it shall maintain such acceptable insurance for the construction period of the authorised works from the proposed date of commencement of construction of the authorised works) and the protected person has confirmed the same in writing to the undertaker.

(5)

Notwithstanding any other provision in this Schedule and or the provisions of sub-paragraph 7(2) of this Schedule and for the avoidance of doubt, the protected person shall not be deemed whether by admission, approval, consent, confirmation, acknowledgement, inspection or otherwise to have assumed any responsibility for the plan or any authorised works (without limitation) carried out or to be carried out nor shall the protected person be deemed to have accepted, acknowledged or given or made any representation that the authorised works shall not cause any damage to any Apparatus.