Regulation 40 Completion certificate applications: time limitI1

England and Wales

(1)

Where the building control authority receives a completion certificate application in relation to HRB work, a stage of HRB work or work to existing HRB which is valid, the building control authority must—

(a)

determine it within 8 weeks beginning with the date the application is received by the building control authority, or

(b)

within such longer period as at any time the building control authority and the applicant agree in writing.

(2)

A completion certificate application is valid if it complies with regulation 39.

Annotations

Commencement

I1

Reg. 40 in force at 1.7.2026, see reg. 1(3)