Regulation 50 Section 30A applications: procedureI1
England and Wales
An application under section 30A of the 1984 Act (“section 30A application”) must be made in writing to the Welsh Ministers by the client for the work to which the original application relates (in this Part F1, except in regulation 46, “the applicant”) and accompanied by the documents specified in paragraph (3).
A section 30A application must be made no later than 6 weeks after the day the relevant period in relation to the application ends.
The documents to accompany a section 30A application are—
a copy of the original application given to the building control authority (including all documentation that accompanied the application);
all information provided to the building control authority in relation to the original application by the applicant;
all correspondence and further information between the applicant and the building control authority in relation to that application;
a copy of the notice sent to the building control authority under paragraph (4);
where the application is made by someone on behalf of the client, a statement signed by the client confirming they agree to the application being made and that the information contained in the application is correct.
At least 2 working days before submitting the application under paragraph (1) the applicant must give notice to the building control authority of their intention to do so.
In this regulation “relevant period” has the meaning given in section 30A(9) of the 1984 Act.
Annotations
Textual amendments
- F1
Words in reg. 50(1) inserted (20.7.2026) by The Building etc. (Amendment) (No. 2) (Wales) Regulations 2026 (W.S.I. 2026/112), regs. 1(2), 7(15)