Regulation 57 Contraventions by the building control authority not to be subject to enforcementI1
England and Wales
The following provisions of these Regulations are prescribed for the purposes of sections 35(2) and 35B(7)(a) of the 1984 Act—
regulation 5 (building control approval applications for HRB work or stage of HRB work: time limit);
regulation 6(1) and (2) (building control approval applications for HRB work or stage of HRB work: consultation);
regulation 7(1), (4) to (6) and (12) (building control approval applications for HRB work or stage of HRB work: decisions);
regulation 9(5) (notice before starting on site and further notice when work is “commenced”);
regulation 13 (building control approval applications for work to existing HRB: time limit);
regulation 14(1) and (2) (building control approval applications for work to existing HRB: consultation);
regulation 15(1), (4) to (6) and (12) (building control approval applications for work to existing HRB: decisions);
regulation 17(4) (notice before starting on site and further notice when work is “commenced”);
regulation 22 (change control applications: time limit);
regulation 23(1) and (2) (change control applications: consultation);
regulation 24(1), (4) to (6) and (9)(b) and (d) (change control applications: decisions);
regulation 30(4) and (6) to (7) (variation of a requirement imposed on a building control approval);
regulation 40 (completion certificate applications: time limit);
regulation 41(1) (completion certificate applications: consultation);
regulation 42 (completion certificate applications: inspection);
regulation 43(1) to (5) and (8) (completion certificate applications: decisions);
regulation 44(5), (7), (9) to (13) and (16) (partial completion certificates);
regulation 46(6) (regularisation of unauthorised building work);
regulation 52 (section 30A applications: determinations);
regulation 53 (section 30A applications: appointed persons).