Schedule SCHEDULE SUBSTITUTED FOR SCHEDULE 2
“SCHEDULE 2
TABLE OF FEES
Regulation 7
£ 1Application for warrant (including issue of warrant) for —
(a)erection, alteration or extension of a building (whether or not combined with application for warrant for change of use) —
(i)where the estimated cost of the operations does not exceed £1,000
12 (ii)where the estimated cost of the operations exceeds £1,000 but does not exceed £10,000 —
(a)the sum of
12
plus (b) for every £500 or part thereof exceeding £1,000
5 (iii)where the estimated cost of the operations exceeds £10,000 but does not exceed £20,000 —
(a)the sum of
100
plus (b) for every £1,000 or part thereof exceeding £10,000
6 (iv)where the estimated cost of the operations exceeds £20,000 but does not exceed £100,000 —
(a)the sum of
160
plus (b) for every £5,000 or part thereof exceeding £20,000
12 (v)where the estimated cost of the operations exceeds £100,000 but does not exceed £500,000 —
(a)the sum of
350
plus (b) for every £50,000 or part thereof exceeding £100,000
90 (vi)where the estimated cost of the operations exceeds £500,000 but does not exceed £1,000,00 —
(a)the sum of
1,070
plus (b) for every £100,000 or part thereof exceeding £500,000
120 (vii)where the estimated cost of the operations exceeds £1,000,000 —
(a)the sum of
1,670
plus (b) for every £200,000 or part thereof exceeding £1,000,000
180 (b)change of use only
12 (c)demolition of a building
12 2Application for amendment of warrant —
(a)for additional operations where the estimated cost of these falls within any of the sub-paragraphs detailed in paragraph 1(a) of this Schedule—fee in accordance with appropriate sub-paragraph of paragraph 1(a) hereof
(b)where no additional operations are involved
12 3Application for extension of a period of a warrant for a building intended to have a limited life
12 ”