Schedule 1 SCHEDULE SUBSTITUTED FOR SCHEDULE 2 WITH EFFECT FROM 24TH JULY 1995
“SCHEDULE 2
TABLE OF FEES
Regulation 7
£ 1Application for warrant (including issue of warrant) for erection, alteration, extension or demolition of a building (whether or not combined with application for warrant for change of use)—
(i)where the estimated cost of the operations does not exceed £2,000
40 (ii)where the estimated cost of the operations exceeds £2,000 but does not exceed £10,000—
(a)the sum of
40
plus
(b)for every £500 or part thereof exceeding £2,000
10 (iii)where the estimated cost of the operations exceeds £10,000 but does not exceed £20,000—
(a)the sum of
200
plus
(b)for every £1,000 or part thereof exceeding £10,000
12 (iv)where the estimated cost of the operations exceeds £20,000 but does not exceed £100,000—
(a)the sum of
320
plus
(b)for every £5,000 or part thereof exceeding £20,000
24 (v)where the estimated cost of the operations exceeds £100,000 but does not exceed £500,000—
(a)the sum of
704
plus
(b)for every £50,000 or part thereof exceeding £100,000
180 (vi)where the estimated cost of the operations exceeds £500,000 but does not exceed £1,000,000—
(a)the sum of
2,144
plus
(b)for every £100,000 or part thereof exceeding £500,000
240 (vii)where the estimated cost of the operations exceeds £1,000,000—
(a)the sum of
3,344 (b)for every £200,000 or part thereof exceeding £1,000,000
360 2Application for warrant (including issue of warrant) for change of use only
25 3Application for amendment of warrant—
(a)for additional operations where the estimated cost of these falls within any of the sub-paragraphs detailed in paragraph 1 of this Schedule—
fee in accordance with appropriate sub-paragraph of paragraph 1 hereof
(b)where no additional operations are involved
25 4Application for extension of a period of a warrant.
25 ”.