Regulation 8 Building warrants: rejection of applications
(1)
An application shall not be treated as received unless the application has been submitted and the prescribed fee paid.
(2)
Except where regulation 4(2) and Schedule 2, section G, paragraph 10 apply, in the event that an application is submitted without the specified plans, the verifier shall–
(a)
advise the applicant that the specified plans are required; and
(b)
accept the application form on condition that the applicant will submit the said plans within the period of 42 days beginning with the date of receipt of the advice referred to in paragraph (2)(a) after which time the verifier may consider the application withdrawn and return the papers relating to the application to the applicant together with the prescribed fee.