Regulation 9 Determination of application
On receipt of an application the verifier shall proceed forthwith to consider the application; and
if satisfied in accordance with section 9(1) of the Act and that the application complies with these regulations grant the application; or
within the period of three months beginning with the date of receipt of the application prepare and send to the applicant or a duly authorised agent a report thereon (“the first report”) identifying what further information is needed to assess the application, and anything which is not in accordance with section 9 (1) of the Act; or
subject to paragraph (2) refuse the application; and
within the period of 14 days beginning with the date of receipt of the application send a copy of the application or of its refusal as appropriate to the local authority for registration in the building standards register.
The verifier shall not refuse the application on any ground without first giving the applicant notification of the proposed ground of refusal and an opportunity of being heard and of making written representations, and the verifier shall in any such case, before finally determining the application, consider any oral and written representations so made by the applicant or the applicant’s duly authorised agent within the period of 14 days beginning with the date on which the notification was given.
In the event that the verifier refuses an application the verifier shall give reasons therefor.