Regulation 35 Exception to building control prohibition: work to occupied buildingsI1
England and Wales
An applicable person is not prohibited from—
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
giving an application for building control approval to a building control authority;
giving an initial notice within the meaning of section 47 of the Building Act 1984 (giving and acceptance of initial notice); F3...
giving an amendment notice within the meaning of section 51A of the Building Act 1984 (variation of work to which initial notice relates); or
giving a building notice within the meaning of regulation 2 of the Building Regulations 2010 (interpretation),
in relation to relevant building work to be carried out to an existing occupied building where on the application date the work had not started.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Where an application for building control approval has been given pursuant to paragraph (1), a building control authority is not prohibited from granting a building control approval to the applicable person.
Where an initial notice is given pursuant to paragraph (1) the local authority is not prohibited from giving the applicable person a notice accepting or rejecting that initial notice under section 47 of the Building Act 1984.
Where an amendment notice is given pursuant to paragraph (1), the local authority is not prohibited from giving the applicable person a notice accepting or rejecting that amendment notice under section 51A of the Building Act 1984.
Where relevant building work is carried out to an existing occupied building following the depositing or giving of a document under paragraph (1)—
then the applicable person is not prohibited from giving—
a notice under regulation 16(4) of the Building Regulations 2010 (notices in relation to building work) in relation to the work;
an application for a certificate under regulation 40 (completion certificate applications) of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 in relation to the work;
a notice under regulation 16(5) of the Building Regulations 2010 (notices in relation to building work) in relation to the work;
an application for a certificate under regulation 45 (partial completion certificates) of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 in relation to the work;
a request for a plans certificate under section 50(1) (plans certificate) of the Building Act 1984 in relation to the work;
then, in respect of the work, a person may give to the applicable person—
a plans certificate within the meaning of section 50 (plans certificate) of the Building Act 1984 in relation to the work;
a final certificate within the meaning of section 51 (final certificate) of the Building Act 1984 in relation to the work.
Where paragraph (4) applies, the relevant authority is not prohibited from giving the person a completion certificate under regulation 17 (completion certificates) or regulation 17A (certificate for building occupied before work is completed) of the Building Regulations 2010 in relation to the work.
Where paragraph (4) applies the F13relevant authority is not prohibited from giving the person a certificate under regulation 18 of the Building Regulations 2010 in relation to the work.
Where paragraph (4) applies, the regulator is not prohibited from giving the applicable person a certificate under regulation 47 (regularisation of unauthorised building work) of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023.
Where paragraph (4) applies, the local authority is not prohibited from giving the person a notice accepting or rejecting that plans certificate under section 50 of the Building Act 1984.
Where paragraph (4) applies the local authority is not prohibited from giving the person a notice accepting or rejecting that final certificate under section 51 of the Building Act 1984.
In this regulation—
“application date” means the date on which the document referred to in paragraph (1) is deposited or given by the applicable person;
F16“building control authority” has the meaning given in regulation 2 of the Building Regulations 2010;
“dwelling” has the meaning in regulation 2 of the Building Regulations 2010;
“material change of use” has the meaning in regulation 5 of the Building Regulations 2010;
“occupied”, in relation to a building, means at least one dwelling contained in the building is occupied by an arm’s length third party on the application date;
“relevant authority” has the meaning given in regulation 2 of the Building Regulations 2010;
“relevant building work” means any building work except work done to give effect to a material change of use of the building or part of the building.
Annotations
Textual amendments
- F1
Reg. 35(1)(a) omitted (1.6.2026) by virtue of The Building Safety (Responsible Actors Scheme and Prohibitions) (Amendment) Regulations 2026 (S.I. 2026/509), regs. 1(1), 9(2)
- F2
Reg. 35(1)(aa) inserted (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 21(3)(a) (with regs. 22-24)
- F3
Word in reg. 35(1)(b) omitted (1.6.2026) by virtue of The Building Safety (Responsible Actors Scheme and Prohibitions) (Amendment) Regulations 2026 (S.I. 2026/509), regs. 1(1), 9(3)
- F4
Reg. 35(1)(ba) inserted (1.6.2026) by The Building Safety (Responsible Actors Scheme and Prohibitions) (Amendment) Regulations 2026 (S.I. 2026/509), regs. 1(1), 9(4)
- F5
Reg. 35(2) omitted (1.6.2026) by virtue of The Building Safety (Responsible Actors Scheme and Prohibitions) (Amendment) Regulations 2026 (S.I. 2026/509), regs. 1(1), 9(5)
- F6
Reg. 35(2A) inserted (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 21(3)(b) (with regs. 22-24)
- F7
Reg. 35(3A) inserted (1.6.2026) by The Building Safety (Responsible Actors Scheme and Prohibitions) (Amendment) Regulations 2026 (S.I. 2026/509), regs. 1(1), 9(6)
- F8
Reg. 35(4)(a)(i) substituted (1.6.2026) by The Building Safety (Responsible Actors Scheme and Prohibitions) (Amendment) Regulations 2026 (S.I. 2026/509), regs. 1(1), 9(7)(a)
- F9
Reg. 35(4)(a)(ia) inserted (1.10.2023) by The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 (S.I. 2023/909), regs. 1(1), 65(4)(a)(i) (with Sch. 3 Pt. 1)
- F10
Reg. 35(4)(a)(ii) substituted (1.6.2026) by The Building Safety (Responsible Actors Scheme and Prohibitions) (Amendment) Regulations 2026 (S.I. 2026/509), regs. 1(1), 9(7)(b)
- F11
Reg. 35(4)(a)(iia) inserted (1.10.2023) by The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 (S.I. 2023/909), regs. 1(1), 65(4)(a)(ii) (with Sch. 3 Pt. 1)
- F12
Reg. 35(4A) inserted (1.6.2026) by The Building Safety (Responsible Actors Scheme and Prohibitions) (Amendment) Regulations 2026 (S.I. 2026/509), regs. 1(1), 9(8)
- F13
Words in reg. 35(5) substituted (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 21(3)(c) (with regs. 22-24)
- F14
Reg. 35(5A) inserted (1.10.2023) by The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 (S.I. 2023/909), regs. 1(1), 65(4)(b) (with Sch. 3 Pt. 1)
- F15
Reg. 35(5B) inserted (1.6.2026) by The Building Safety (Responsible Actors Scheme and Prohibitions) (Amendment) Regulations 2026 (S.I. 2026/509), regs. 1(1), 9(9)
- F16
Words in reg. 35(7) inserted (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 21(3)(d) (with regs. 22-24)
Commencement
- I1
Reg. 35 in force at 4.7.2023, see reg. 1(1)