Paragraph 14 Construction lighting
(1)
No phase is to be commenced until a detailed construction lighting design strategy for that phase has been submitted to and approved in writing by the relevant planning authority.
(2)
Each detailed construction lighting design strategy must accord with the measures set out in the lighting design strategy.
(3)
Each phase must be carried out in accordance with the approved detailed construction lighting design strategy.