The Cambridge Waste Water Treatment Plant Relocation Order 2025
S.I. 2025/452 · Made 2 April 2025
Infrastructure Planning
Made 2nd April 2025
Coming into force 23rd April 2025
The application was examined in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3 by a panel of 3 members (“the Panel”) appointed by the Secretary of State in accordance with Chapter 2 of Part 6 of the 2008 Act.
The Panel, having examined the application with the documents that accompanied the application, and the representations made and not withdrawn, has, in accordance with section 74(2) of the 2008 Act, made a report and recommendation to the Secretary of State.
The Secretary of State, having considered the representations made and not withdrawn and the report of the Panel, has decided to make an Order granting development consent for the development described in the application with modifications which in the opinion of the Secretary of State do not make any substantial change to the proposals comprised in the application.
The Secretary of State in exercise of the powers conferred by sections 114f4, 115f5, 117f6, 120f7, 122f8 and 123f9 of, and paragraphs 1 to 4, 8, 10 to 15, 17, 20, 22, 23, 26, 33 to 37 of Part 1 of Schedule 5f10 to, the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20). Section 37 was amended by sections 128(2) and 137 of, and paragraphs 1 and 5 of Part 1 of Schedule 13 to, the Localism Act 2011 (c. 20).
- f2
-
S.I. 2009/2264, amended by S.I. 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, S.I. 2014/469, S.I. 2014/2381, S.I. 2015/377, S.I. 2015/1682, S.I. 2017/524, S.I. 2017/572, S.I. 2018/378, S.I. 2019/734, S.I. 2020/764, S.I. 2020/1534, S.I. 2021/978, S.I. 2022/634, S.I. 2023/1071 and S.I. 2024/332.
- f3
-
S.I. 2010/103, amended by S.I. 2012/635 and S.I. 2024/317.
- f4
-
Section 114 was amended by paragraph 55 of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20).
- f5
-
Section 115 was amended by paragraph 56 of Part 1 of Schedule 13 and Part 20 of Schedule 25 to the Localism Act 2011 (c. 20), section 160 of the Housing and Planning Act 2016 (c. 22) and section 43 of the Wales Act 2017 (c. 4).
- f6
-
Section 117 was amended by paragraph 58 of Part 1 of Schedule 13 and Part 20 of Schedule 25 to the Localism Act 2011 (c. 20).
- f7
-
Section 120 was amended by section 140 and paragraph 60 of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20).
- f8
-
Section 122 was amended by paragraph 62 of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20).
- f9
-
Section 123 was amended by paragraph 62 of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20).
- f10
-
Part 1 of Schedule 5 was amended by paragraph 4 of Part 1 of Schedule 8 and Part 2 of Schedule 22 to the Marine and Coastal Access Act 2009 (c. 23), paragraph 71 of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20) and paragraph 76 of Part 3 of Schedule 6 to the Wales Act 2017 (c. 4).
Contents
- Part 1: PRELIMINARY
- 1Citation and Commencement
- 2Interpretation
- Part 2: PRINCIPAL POWERS
- 3Development consent etc granted by the Order
- 4Authorisation of use
- 5Maintenance of authorised development
- 6Limits of deviation
- 7Benefit of Order
- 8Transfer of benefit of Order
- 9Defence to proceedings in respect of statutory nuisance
- Part 3: STREETS
- 10Street works
- 11Power to alter layout, etc, of streets
- 12Temporary stopping up of streets
- 13Public rights of way – creation, temporary stopping up and diversion
- 14Access to works
- 15Maintenance of highway works
- 16Speed limits
- 17Traffic regulation
- 18Agreements with highway authorities
- Part 4: SUPPLEMENTAL POWERS
- 19Discharge of water
- 20Protective works to buildings and structures
- 21Authority to survey and investigate the land
- 22Removal of human remains
- 23Felling or lopping of trees and removal of hedgerows
- 24Trees subject to tree preservation orders
- 25Trees in conservation areas
- Part 5: ACQUISITION AND POSSESSION OF LAND
- 26Compulsory acquisition of land
- 27Time limit for exercise of authority to acquire land compulsorily
- 28Compulsory acquisition of rights and imposition of restrictive covenants
- 29Acquisition of subsoil only
- 30Acquisition of land limited to subsoil lying more than 7 metres beneath surface
- 31Private Rights
- 32Power to override easements and other rights
- 33Application and modification of the 1981 Act
- 34Modification of Part 1 of the 1965 Act
- 35Temporary use of land for carrying out the authorised development
- 36Temporary use of land for maintaining the authorised development
- 37Disregard of certain interests and improvements
- 38Set-off for enhancement in value of retained land
- 39No double recovery
- 40Compulsory acquisition of land – incorporation of the mineral code
- 41Statutory undertakers
- 42Recovery of costs of new connections
- 43Rights under or over streets
- Part 6: MISCELLANEOUS AND GENERAL
- 44Rights on the river Cam
- 45Application of landlord and tenant law
- 46Operational land for the purposes of the 1990 Act
- 47Protective Provisions
- 48Discharge of requirements and other approvals etc
- 49Application, disapplication and modification of legislative provisions
- 50Crown rights
- 51Certification of plans etc.
- 52Arbitration
- 53Service of notices
- Signature
- Schedule 1AUTHORISED DEVELOPMENT
- Schedule 2: REQUIREMENTS
- Part 1: REQUIREMENTS
- 1Paragraph 1
- 2Time limit
- 3Phasing
- 4Parameters of authorised development
- 5Requirement for written approval
- 6Approved details and amendments to them
- 7Detailed design
- 8Code of construction practice
- 9Construction environmental management plans
- 10Outfall
- 11Landscape, ecological and recreational management plan
- 12Operational workers travel plan
- 13Archaeological investigation mitigation strategy
- 14Construction lighting
- 15Drainage
- 16Contamination risk
- 17Decommissioning
- 18Operational Asset Management Plan
- 19Operational logistics traffic plan
- 20Odour management plan
- 21Carbon management plan
- 22Operational water quality monitoring plan
- 23Discovery centre
- 24Operational Wildlife Hazard Management Plan
- 25Biodiversity net gain
- 26Temporary stopping up of public rights of way
- 27Bridleway
- Part 2: PROCEDURE FOR DISCHARGE OF CERTAIN APPROVALS
- 1Applications made for certain approvals
- 2Further information
- 3Appeals
- 4Interpretation of Part 2 of Schedule 2
- Schedule 3STREETS SUBJECT TO STREET WORKS
- Schedule 4STREETS SUBJECT TO ALTERATION OF LAYOUT
- Schedule 5STREETS TO BE TEMPORARILY STOPPED UP
- Schedule 6: PUBLIC RIGHTS OF WAY
- 1PUBLIC RIGHTS OF WAY TO BE TEMPORARILY STOPPED UP FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
- 2NEW PUBLIC RIGHT OF WAY TO BE CREATED
- Schedule 7ACCESS TO WORKS
- Schedule 8: SPEED LIMITS
- 1TEMPORARY SPEED LIMITS
- 2PERMANENT SPEED LIMITS
- Schedule 9: TRAFFIC REGULATION
- 1TEMPORARY
- 2PROHIBITED MOVEMENTS
- Schedule 10LAND IN WHICH ONLY NEW RIGHTS ETC MAY BE ACQUIRED
- Schedule 11LAND OF WHICH ONLY SUBSOIL MORE THAN 7 METRES BENEATH THE SURFACE MAY BE ACQUIRED TOGETHER WITH NEW RIGHTS AND/OR RESTRICTIVE COVENANTS
- Schedule 12LAND OF WHICH TEMPORARY POSSESSION ONLY MAY BE TAKEN
- Schedule 13: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND THE IMPOSITION OF RESTRICTIVE COVENANTS
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Application of Part 1 of the 1965 Act
- 5Application of Part 1 of the 1965 Act
- 6Application of Part 1 of the 1965 Act
- 7Application of Part 1 of the 1965 Act
- 8Application of Part 1 of the 1965 Act
- 9Application of Part 1 of the 1965 Act
- 10Application of Part 1 of the 1965 Act
- Schedule 14: PARAMETERS
- 1TERMINAL PUMPING STATION (WORK No. 16)
- 2STORM TANKS (WORK No. 14)
- 3INLET WORKS (WORK No. 4)
- 4PRIMARY SETTLEMENT TANKS (WORK No. 6)
- 5ACTIVATED SLUDGE PROCESS TANKS (WORK No. 10)
- 6FINAL SETTLEMENT TANKS (WORK No. 11)
- 7TERTIARY TREATMENT PLANT (WORK No. 13)
- 8SLUDGE STORAGE CAPACITY (WORK No. 8)
- 9THICKENING EQUIPMENT (WORK No. 8)
- 10ODOUR CONTROL PLANT (WORK No. 8)
- 11DIGESTERS (WORK No. 8)
- 12CAKE DEWATERING AND STORAGE (WORK No. 8)
- 13LIQUOR TREATMENT PLANT (WORK No. 8)
- 14NUTRIENT RECOVERY OPTION (WORK No. 8)
- 15GAS HANDLING EQUIPMENT OPTIONS (WORK Nos. 8 and 9)
- 16STEAM RAISING BOILER (WORK No. 8)
- 17INTERNAL ROADS (FURTHER WORKS WITHIN THE INNER BOUNDARY OF WORK No. 15)
- 18BUILDINGS AND OTHER FACILITIES (WORK Nos. 3, 7, 19 and FURTHER WORKS)
- 19CONSTRUCTION COMPOUNDS (WORK Nos. 18, 25, 28, 32 and 34)
- 20TRANSFER TUNNEL (WORK Nos. 18 and 27)
- 21OUTFALL STRUCTURE (WORK No. 32)
- 22SOLAR INSTALLATION (WORK Nos. 7, 15 and 19)
- 23HEIGHTS OF SLIM STRUCTURES NOT INCLUDED IN OTHER PARTS
- 24PARAPET OVER THE A14 (WORK No. 1)
- Schedule 15: PROTECTIVE PROVISIONS
- Part 1: FOR THE PROTECTION OF ELECTRICITY AND GAS UNDERTAKERS
- 1Application
- 2Application
- 3Precedence of the 1991 Act in respect of apparatus in the streets
- 4Removal of apparatus
- 5Facilities and rights for alternative apparatus
- 6Retained apparatus
- 7Expenses and costs
- 8Compensation
- Part 2: FOR THE PROTECTION OF EASTERN POWER NETWORKS PLC
- 9Application
- 10Interpretation
- 11On-street apparatus
- 12Temporary closure of streets
- 13Acquisition of land
- 14Removal of apparatus
- 15Facilities and rights for alternative apparatus
- 16Retained apparatus
- 17Expenses
- 18Indemnity
- Part 3: FOR THE PROTECTION OF CADENT GAS LIMITED AS GAS UNDERTAKER
- 19Application
- 20Interpretation
- 21On street apparatus
- 22Apparatus of Cadent in stopped up streets
- 23Protective works to buildings
- 24Acquisition of land
- 25Removal of apparatus
- 26Facilities and rights for alternative apparatus
- 27Retained apparatus: protection of Cadent
- 28Expenses
- 29Indemnity
- 30Enactments and agreements
- 31Co-operation
- 32Access
- 33Arbitration
- 34Notices
- Part 4: FOR THE PROTECTION OF RAILWAY INTERESTS
- 35Paragraph 35
- 36Paragraph 36
- 37Paragraph 37
- 38Paragraph 38
- 39Paragraph 39
- 40Paragraph 40
- 41Paragraph 41
- 42Paragraph 42
- 43Paragraph 43
- 44Paragraph 44
- 45Paragraph 45
- 46Paragraph 46
- 47Paragraph 47
- 48Paragraph 48
- 49Paragraph 49
- 50Paragraph 50
- 51Paragraph 51
- 52Paragraph 52
- 53Paragraph 53
- 54Paragraph 54
- Part 5: FOR THE PROTECTION OF NATIONAL HIGHWAYS LIMITED
- 55Application etc.,
- 56Interpretation
- 57General
- 58General
- 59Works outside the Order limits
- 60Prior approvals and security
- 61Construction of the specified works
- 62Payments
- 63Provisional Certificate
- 64Opening
- 65Final condition survey
- 66Defects Period
- 67Final Certificate
- 68Security
- 69Commuted sums
- 70Insurance
- 71Indemnity
- 72Maintenance of the specified works
- 73Land or rights
- 74Expert Determination
- Part 6: FOR THE PROTECTION OF LOCAL HIGHWAY AUTHORITIES
- 75Application etc.
- 76Interpretation
- 77Interpretation
- 78Dispositions
- 79Prior approvals and security
- 80Construction of the specified works
- 81Programme and method statement/commencement of the specified works
- 82Deviations from approved programme and method statement and traffic management proposals
- 83Completion of the works
- 84Access, inspection and testing
- 85Inspection and testing (covered work and foundations)
- 86Statutory undertakers (highways)
- 87Progress of the specified works
- 88Provisional Certificate of Completion
- 89Maintenance and defects correction
- 90Stage 4 safety audit
- 91Final Certificate
- 92Indemnity
- 93Insurance
- 94Variation to council specification and approved drawings
- 95Default
- 96CDM Regulations
- 97Telecommunications apparatus
- 98Commuted sum and asset fees
- 99Safety Audit Costs
- 100Cash Deposit
- 101Dispute provisions
- 102Documents submitted for approval
- 103Agreement Fee
- 104Additional technical vetting costs
- 105Submissions of Drawings
- 106As built drawings
- Part 7: FOR THE PROTECTION OF THE RELEVANT NAVIGATION AUTHORITY
- 107Paragraph 107
- 108Paragraph 108
- 109River works
- 110Details for approval
- 111Intention to commence Work No. 31 and Work No. 32
- 112Expenses
- 113Indemnity
- 114Disputes
- Part 8: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
- 115Paragraph 115
- 116Paragraph 116
- 117Paragraph 117
- 118Paragraph 118
- 119Paragraph 119
- 120Paragraph 120
- 121Paragraph 121
- 122Paragraph 122
- Part 9: FOR THE PROTECTION OF CAMBRIDGE WATER
- 123Paragraph 123
- 124Paragraph 124
- 125Paragraph 125
- 126Apparatus of Cambridge Water
- 127Apparatus of Cambridge Water
- 128Apparatus of Cambridge Water
- 129Acquisition of land
- 130Acquisition of land
- 131Acquisition of land
- 132Access
- 133Unmapped apparatus
- 134Costs
- 135Expenses
- 136Co-operation
- Part 10: FOR THE PROTECTION OF THE LEAD LOCAL FLOOD AUTHORITY
- 137Paragraph 137
- 138Paragraph 138
- 139Paragraph 139
- 140Paragraph 140
- 141Paragraph 141
- 142Paragraph 142
- 143Paragraph 143
- Schedule 16: REMOVAL OF HEDGEROWS
- 1REMOVAL OF HEDGEROWS
- 2REMOVAL OF IMPORTANT HEDGEROWS
- Schedule 17: MISCELLANEOUS CONTROLS
- 1Introduction
- 2Highways Act 1980
- 3Party Wall etc Act 1996
- 4Planning Act 2008 – Application of the 2010 Regulations (Community infrastructure Levy)
- 5Town and Country Planning Act 1990
- 6Flood and Water Management Act 2010
- 7Control of Pollution Act 1974
- 8Burial Act 1857
- Schedule 18CERTIFICATION OF PLANS AND DOCUMENTS
- Schedule 19: ARBITRATION RULES
- 1Primary objective
- 2Time periods
- 3Timetable
- 4Procedure
- 5Arbitrator’s powers
- 6Costs
- 7Confidentiality
- Explanatory note