Part 18 BUILDINGS AND OTHER FACILITIES (WORK Nos. 3, 7, 19 and FURTHER WORKS)

Original text. Later amendments are not shown.

(1) Item(2) Main parameters(3) Maximum height
Gateway building (Work No. 19)58.2m x 17.1m

18.5m AOD (9m above FGL)

Piled foundations to a depth of -15.5m AOD (25m below FGL)

 

Workshop building (Work No. 7)55m x 16m

19.5m AOD (10m above FGL)

Piled foundations to a depth of -15.5m AOD (25m below FGL)

 

District Network Operator (DNO) enclosure (Work No. 19)5m x 10m12.5m AOD (3m above FGL)
Vehicle parking (Work Nos. 3, 7 and Further Works)4,000m2N/A

56 staff (including LGVs);

7 HGVs;

3 trailers;

12 visitor vehicle parking spaces (including two disabled spaces);

1 visitor coach parking space

Provision for 50 bicycles