Schedule 14 PARAMETERS
- 1TERMINAL PUMPING STATION (WORK No. 16)
- 2STORM TANKS (WORK No. 14)
- 3INLET WORKS (WORK No. 4)
- 4PRIMARY SETTLEMENT TANKS (WORK No. 6)
- 5ACTIVATED SLUDGE PROCESS TANKS (WORK No. 10)
- 6FINAL SETTLEMENT TANKS (WORK No. 11)
- 7TERTIARY TREATMENT PLANT (WORK No. 13)
- 8SLUDGE STORAGE CAPACITY (WORK No. 8)
- 9THICKENING EQUIPMENT (WORK No. 8)
- 10ODOUR CONTROL PLANT (WORK No. 8)
- 11DIGESTERS (WORK No. 8)
- 12CAKE DEWATERING AND STORAGE (WORK No. 8)
- 13LIQUOR TREATMENT PLANT (WORK No. 8)
- 14NUTRIENT RECOVERY OPTION (WORK No. 8)
- 15GAS HANDLING EQUIPMENT OPTIONS (WORK Nos. 8 and 9)
- 16STEAM RAISING BOILER (WORK No. 8)
- 17INTERNAL ROADS (FURTHER WORKS WITHIN THE INNER BOUNDARY OF WORK No. 15)
- 18BUILDINGS AND OTHER FACILITIES (WORK Nos. 3, 7, 19 and FURTHER WORKS)
- 19CONSTRUCTION COMPOUNDS (WORK Nos. 18, 25, 28, 32 and 34)
- 20TRANSFER TUNNEL (WORK Nos. 18 and 27)
- 21OUTFALL STRUCTURE (WORK No. 32)
- 22SOLAR INSTALLATION (WORK Nos. 7, 15 and 19)
- 23HEIGHTS OF SLIM STRUCTURES NOT INCLUDED IN OTHER PARTS
- 24PARAPET OVER THE A14 (WORK No. 1)