Paragraph 3 I1
England, Wales and Scotland
Any specified or protective works must, when commenced, be constructed—
(a)
without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled in accordance with this Part of this Schedule and with any requirements made under paragraph 2(3);
(b)
under the supervision (if given) and to the reasonable satisfaction of the engineer; and
(c)
in such manner as to cause as little detriment as is reasonably practicable.
Annotations
Commencement
- I1
Sch. 10 para. 3 in force at 21.10.2014, see art. 1