Paragraph 10 I1
England, Wales and Scotland
(1)
No part of the authorised development is to commence until written details of the materials to be used for the surfacing of the new road comprised in Work No. 1 and the adjacent cycle track and footway have been submitted to and approved in writing by the relevant planning authority.
(2)
The details submitted under sub-paragraph (1) must include provision for the use of low noise road surfacing materials on the road comprised in Work No. 1.
(3)
The authorised development must be carried out using the materials approved under sub-paragraph (1).
Annotations
Commencement
- I1
Sch. 2 para. 10 in force at 21.10.2014, see art. 1