OpenLegislation

Schedule 9 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1

England, Wales and Scotland

(1)

Location

(2)

Number of land shown on the land plans

(3)

Purpose for which temporary possession may be taken

(4)

Relevant part of the authorised development

District of Central Bedfordshire01/09Landscaping, removal of redundant overhead power lines, construction of footway and cycle track alongside Sandringham Drive.

Work No. 1

Work No. 6

Work No. 7

01/13Landscaping.

Work No. 1

Work No. 2

Work No. 6

01/16Landscaping.

Work No. 1

Work No. 6

01/17Landscaping, installation of underground service ducts.Work No. 1
01/19Landscaping, installation of underground service ducts.Work No. 1
01/21Landscaping, installation of underground service ducts.

Work No. 1

Work No. 7

02/05Landscaping and works to Houghton Brook.

Work No. 1

Work No. 8

02/06Landscaping, installation of underground service ducts, working space.Work No. 1
02/10Improvement of Parkside Drive, access to works.

Work No. 8

Work No. 9

02/11Improvement of Parkside Drive, access to works.Work No. 9
02/24Removal of redundant parts of Parkside Drive, landscaping.Work No. 10
02/25Storage of topsoil and excavated material.Work No. 1
02/26Storage of topsoil and excavated material, haul road, working space.Work No. 1
02/27Storage of topsoil and excavated material, haul road, working space.Work No. 1
02/30Landscaping, haul road, working space, removal of redundant overhead power lines.

Work No. 1

Work No. 14

02/31Working space to construct bridge.Work No. 1
02/32Working space to construct bridge.Work No. 1
02/35LandscapingWork No. 9
02/36LandscapingWork No. 9
02/37LandscapingWork No. 9
02/38LandscapingWork No. 9
02/39Landscaping, removal of redundant overhead power lines, improvement of footway and cycle track between Frogmore Road and Wheatfield Road.

Work No. 7

Work No. 8

02/40Landscaping, installation of underground service ducts, improvement of footway and cycle track between Frogmore Road and Wheatfield Road.Work No. 1
02/41Landscaping, installation of underground service ducts, working space for the construction of an attenuation pond.Work No. 1
02/46Landscaping, installation of underground service ducts.Work No. 1
02/48Landscaping, haul road, working space, removal of redundant overhead power line.

Work No. 8

Work No. 14

04/02Construction of a private means of access to proposed development.Work No. 1
04/07Haul road, working space.Work No. 1
04/08Haul road, working space.Work No. 1
04/09Haul road, working space.Work No. 1
04/10Haul road, working space.Work No. 1
04/11Construction of a private means of access to farm buildings.Work No. 1
04/12Working spaceWork No. 1
05/09Construction of a private means of access to farm buildings.Work No. 15
05/10Site of a construction compound including temporary access for site vehicles.

Work No. 1

Work No. 12

Work No. 13

Work No. 15

05/11Construction of a private means of access to farm buildings.Work No. 1
05/12Construction of a private means of access to farm buildings.Work No. 1
Borough of Luton01/14Landscaping.Work No. 1
03/05Access for construction of a footway and cycle track, works to Houghton BrookWork No. 14
03/06Access for construction of a footway and cycle track, works to Houghton BrookWork No. 14

Annotations

Commencement

I1

Sch. 9 in force at 21.10.2014, see art. 1