Schedule 1
The works referred to in this Order and shown on the deposited plan marked “The Central Regional Council (Kirkton Burn, Balquhidder) Water Order 1988 Plan and Sections of Works” are—
| Work No. 1 | River training works incorporating a weir with crest level 0.3 metres or thereby above the general bed level of the Kirkton Burn situated at a point 1,250 metres or thereby measured in a straight line north-north-west of kirkton Bridge where the Kingshouse to Balquhidder road crosses the said Kirkton Burn. |
| Work No. 2 | An intake weir with crest level 0.1 metres or thereby above the general bed level of the said Kirkton Burn and a gauging chamber incorporating an approved gauge, situated immediately to the east of Work No. 1. |
| Work No. 3 | A pipe to give residual flow in the said Kirkton Burn leading south from Work No. 2 for a distance of 20 metres or thereby. |
| Work No. 4 | A chamber with approved gauge and a pipe extending 3 metres or thereby from the said chamber north-westwards to Work No. 2. |