OpenLegislation

Paragraph 12

(1)

Subject to sub-paragraph (2) below, the appropriate authority shall repay to the undertakers the reasonable expenses incurred by the undertakers in, or in connection with—

(a)

the removal and relaying or replacing, alteration or protection of any apparatus or the provision and construction of any new apparatus under any of the provisions of this Part of this Schedule;

(b)

the cutting off of any apparatus from any other apparatus; and

(c)

any other work or thing rendered reasonably necessary in consequence of the exercise by the appropriate authority of any of the powers of this Act.

(2)

Section 23(3) and (4) of the M1Public Utilities Street Works Act 1950 (limitations on undertakers’ right to payments) shall, so far as applicable, apply to any payment to be made by the appropriate authority under sub-paragraph (1) above as if the works or operations mentioned in that sub-paragraph were such undertakers’ works as are referred to in the said subsection (3), and as if in that subsection for the words “specified as so necessary in a specification of the works settled under Part I of the Fourth Schedule to this Act or agreed so to be by the promoting authority” there were substituted the words “agreed or determined by arbitration under Part VI of Schedule 7 to the Channel Tunnel Act 1987”.

Annotations

Marginal citations

M1

1950 c.39.