Paragraph 6
Not less than six months before commencing the construction of Works Nos. 3 and 4 and any underground ancillary works associated with those works, the Concessionaires shall, subject to any necessary consents, construct such number of observation boreholes in such positions and equipped with such monitoring equipment as the Authority may reasonably require for the purpose of monitoring the effect of any of those works on groundwater.